Sterling Highway 45 – 60 Project
Spring 2022 Online Public Meeting
April 14 – May 12, 2022
Sterling Highway MP 45 – 60 Project
Spring 2022 Online Public Meeting
April 14 – May 12, 2022
Welcome!
Summer 2022 construction will focus on the current highway at Phase 1A (MP 56-58), the Pioneer Roads, and Tract C. Construction is anticipated to continue through fall 2022, and recreation access will be maintained throughout construction. Design continues on the middle and east end of the project.
For more information, visit sterlinghighway.net or email the project team at [email protected].
Navigating this site:
This site is best viewed on your desktop or laptop computer at 100% view. You may scroll down using your mouse at your leisure to view each station or use the left navigation to skip to different stations. If you prefer to experience this Online Meeting in text format only, visit the Text Only page of this meeting.
Navigating this moblie site:
You may scroll up and down at your leasure. You may also utilize the hamburger menu at the top of your screen.
Let’s get started!
Station 1 - Project Overview Map
Welcome to the Sterling 45-60 Spring 2022 Online Open House Project Overview Map. Hover over the red magnifying circles to see project features.
West End (Phase 1A)
Slaughter Gulch Trail Construction
East End (Phase 1B) Under Design
Intersection of Old and New Sterling Highway
Resurrection Pass Trail Updates
Juneau Creek Bridge – Under Design
New Alignment Map
West End (Phase 1A)
Slaughter Gulch Trail Construction
East End (Phase 1B) Under Design
Intersection of Old and New Sterling Highway
Resurrection Pass Trail Updates
Juneau Creek Bridge – Under Design
New Alignment Map
Phase Segment Information
West End (Phase 1A)
Phase 1A is under construction. Finishing touches are anticipated to take place in spring 2023.
Phase 1A Design Features:
- 12-foot lanes
- 8-foot shoulders
- Wildlife undercrossings
- Rock cuts with mesh retaining walls
East End (Phase 1B)
Intersection of Old and New Sterling Highways
The design was finalized for the intersection at MP 47 connecting the Sterling Highway and the current (Old Sterling) highway as primary access into Cooper Landing.
East End (Phase 1B)
Under Design
- The Quartz Creek Road intersection concept at MP 44.5 is finalized. The connection to the Kenai Peninsula Borough roads is in process.
- Utility relocations are in process. Utility companies are to finalize the preferred utility relocation sites with property owners.
- Construction of Phase 1B will coincide with Phase 3.
Juneau Creek Bridge (Phase 2)
Under Design
- The Value Engineering Study has been completed; it evaluated cost and value of design concepts, including factors such as bridge height, aesthetics, constructability, and trail impacts.
- Suggestions included changing bridge type to rigid structure to reduce cost, open line of sight near trails, and simplified construction and maintenance.
- DOT&PF will use recommendations to adjust bridge design this spring.
New Alignment (Phases 3–6)
Design and Construction
- Highway design is at 95%.
- Features include new pathway along south side of new highway, wildlife crossings, and climbing lanes.
- Land exchange is in progress.
Recreation Access (Phases 3-6)
Resurrection Pass Trail
The parking configuration was adjusted based on feedback from United States Forest Service (USFS) and horse and snow machine user groups.
- New parking and a dedicated left-turn lane will be constructed.
- The new trail will connect the parking lot to Resurrection Pass trail with a separate equestrian access trail.
- The new Juneau Falls Overlook will be accessible via a 1/4-mile trail from the parking lot.
- The parking lot will accommodate the access road and include snow storage
Western Intersection (Phases 3-6)
Tight Diamond Interchange
- Tight diamond interchange design selected for the intersection of new and old Sterling Highways at west end of Phases 3–6.
- Design best for traffic safety and for minimizing impacts on cultural resources and wetlands.
Phase Segment Information
Click on the tabs below to learn more about each project phase.
Click the titles below to expand.
West End (Phase 1A)
Phase 1A is under construction. Finishing touches are anticipated to take place in spring 2023.
Phase 1A Design Features:
- 12-foot lanes
- 8-foot shoulders
- Wildlife undercrossings
- Rock cuts with mesh retaining walls
East End (Phase 1B)
Intersection of Old and New Sterling Highways
The design was finalized for the intersection at MP 47 connecting the Sterling Highway and the current (Old Sterling) highway as primary access into Cooper Landing.
East End (Phase 1B - Under Design)
Under Design
- The Quartz Creek Road intersection concept at MP 44.5 is finalized. The connection to the Kenai Peninsula Borough roads is in process.
- Utility relocations are in process. Utility companies are to finalize the preferred utility relocation sites with property owners.
- Construction of Phase 1B will coincide with Phase 3.
Juneau Creek Bridge (Phase 2)
Under Design
- The Value Engineering Study has been completed; it evaluated cost and value of design concepts, including factors such as bridge height, aesthetics, constructability, and trail impacts.
- Suggestions included changing bridge type to rigid structure to reduce cost, open line of sight near trails, and simplified construction and maintenance.
- DOT&PF will use recommendations to adjust bridge design this spring.
New Alignment (Phases 3–6)
Design and Construction
- Highway design is at 95%.
- Features include new pathway along south side of new highway, wildlife crossings, and climbing lanes.
- Land exchange is in progress.
Recreation Access (Phases 3-6)
Resurrection Pass Trail
The parking configuration was adjusted based on feedback from United States Forest Service (USFS) and horse and snow machine user groups.
- New parking and a dedicated left-turn lane will be constructed.
- The new trail will connect the parking lot to Resurrection Pass trail with a separate equestrian access trail.
- The new Juneau Falls Overlook will be accessible via a 1/4-mile trail from the parking lot.
- The parking lot will accommodate the access road and include snow storage
Western Intersection (Phases 3-6)
Tight Diamond Interchange
-
Tight diamond interchange design selected for the intersection of new and old Sterling Highways at west end of Phases 3–6.
-
Design best for traffic safety and for minimizing impacts on cultural resources and wetlands.
Station 2 - Design Updates
Choose the left and right arrows to navigate this section.
Swipe left to right to navigate this section.
Station 3 - Watershed Connectivity
Station 4 - Schedule & Project Next Steps
Field work, design, and construction activities are underway along the project corridor.
Winter field work at bridge abutments is complete.
- Permitting coordination with agencies is underway for construction activities.
- Summer 2022 construction will focus on Phase 1A (MP 56 to MP 58), Pioneer Roads, and Tract C.
- Water quality testing continues upon request.
- Wildlife camera work is ongoing.
- A large archeology crew is in the field this season completing construction monitoring and data recovery. Findings will be published publicly as allowed on a semiregular basis.
Schedule
Project completion will likely occur in 2027.
Right-of-Way
Coordination with property owners is well underway. Property appraisals are continuing on Phase 1B. The project is coordinating with Kenai Peninsula Borough and USFS to gain access to alignment on existing roadways. Phases 3–5 will not impact private property owners.
Station 5 - Construction
2022 Construction
- Summer 2022 construction focuses on Phase 1A (MP 56 to MP 58), Pioneer Roads, and Tract C.
- Scarsella Bros. are continuing Phase 1A construction.
- Quality Asphalt Paving was selected as the new Construction Manager/General Contractor and will be working on Pioneer Road and Tract C construction.
- Recreation access will be maintained throughout construction.
Know Before You Go
DOT&PF will notify the public about upcoming construction.
Project and road condition information
- AlaskaNavigator.org – construction status. Search for the Sterling Highway MP 45-60 project.
- 511.Alaska.Gov – road conditions – select “My 511” to create an account and sign up for alerts to your phone or email
- Sterlinghighway.net – project updates
Sign up now to receive alerts about changes to traffic patterns so you can plan your travel.
Station 6 - Public Meeting Video
Station 7 - Contact Us & Mailing List Sign-up
Comment - We want to hear from you!
Complete the CAPTCHA math equation to submit your comment.
Join our Emailing List!
Email Us
Visit the Project Website
Give us a call
Construction questions?
Shaun Combs, DOT&PF
907-351-0501
Project questions?
Katherine Wood
907-644-2153
Supporting Documents
The documents below support the information displayed throughout this online public meeting. You will need a PDF reader to view these documents. Download a free version at Adobe’s website.