West End (1A) – MP 56-58

Juneau Creek Bridge Design
Juneau Creek Span Bridge

DOT&PF has completed a Value Engineering Study for the bridge to fine tune bridge design for a variety of considerations including aesthetics, constructability, and trail connections.

Suggestions from the study included using a rigid structure for the bridge to reduce cost, maintaining an open line of sight near trails, and simplifying construction and maintenance.

DOT&PF will use these recommendations to adjust bridge design this spring.

Bridge construction is estimated to start in 2023 and to take 3 years to build, including steel procurement. The bridge is a critical scheduling factor for the entire project.