Welcome to the Sterling Highway MP-45-60 Online Open House
The project is planned to reduce highway congestion, meet current design standards, and improve highway safety.
Construction on the current highway will begin this spring. Design is continuing on the middle and east ends of the project.
For more information, visit sterlinghighway.net or email the project team at [email protected].
Navigating this site:
This site is best viewed on your desktop or laptop computer at 100% view. You may scroll down at your leisure to view each station, use the dot navigation on the right side of your screen or use the top navigation to skip to different stations.
View the full presentation and video:
Let’s get started!
Station 1 - Project Overview Map
Welcome to the Sterling 45-60 Spring 2021 Online Open House Project Overview Map. Hover over the red magnifying circles to see project features.
West End (Phase 1A)
Slaughter Gulch Trail Construction
East End (Phase 1B) Under Design
Intersection of Old and New Sterling Highway
Resurrection Pass Trail Updates
Juneau Creek Bridge – Under Design
New Alignment Map
Map Gallery
Station 2 - Design Updates
Choose the left and right arrows to navigate this section.
Station 3 - Watershed Connectivity
Hydrological mapping is complete. Wetlands are preserved, and culverts, ditches, and wildlife passages will provide watershed connectivity throughout the project area.
Station 4 - Schedule & Project Next Steps
As design continues and construction ramps up, the project will see a robust field season.
- Geotechnical investigations will continue at the bridge site.
- Extensive cultural resources research and monitoring will occur throughout the project.
- Minor wildlife work will continue with a focus on bird and goshawk counts and monitoring cameras at wildlife crossing locations.
- Surveyors will work on trails in some areas.
- Invasive species eradication is occurring now to reduce spread during construction.
- Water quality testing is continuing upon request.
RIGHT-OF-WAY
Coordination with property owners is well underway. Property appraisals are started on Phase 1B. The project is coordinating with KPB & USFS to gain access to alignment on existing roadways. Phases 3-4 will not impact private property owners. The CIRI/USFWS land transfer is still underway.
FIREWOOD
Firewood will be made available to the public again this season. Check the Cooper Landing Crier and project website for notices. Join the project email list for direct notification.
Station 5 - 2021 Construction
Construction is scheduled to increase in 2021.
- Reconstruction will begin on the main highway on Phase 1A, with Scarsella Brothers as the contractor.
- Clearing on the off-alignment and at staging areas will continue.
- Grading and drainage work will begin on sections of the new alignment.
- Sections of the pioneer road will be improved this summer.
The anticipated schedule for 2021 construction on the off-alignment section of the project may shift to take advantage of alternative construction methodologies.
A staging area at MP 45.5, next to the Cooper Landing Brewery, will be used to support construction. The project is coordinating with KPB to assure that land use is consistent with future development.
Recreation access will be maintained on trails throughout construction. Trail users may see signs of construction activity.
Watch for trucks on the road through Cooper Landing. Construction materials will be trucked in from Soldotna and Anchorage.
West End (Phase 1A) Construction
- No major closures are expected this summer.
- Several short nighttime road closures are anticipated during July. A two-week notice is required for closures.
- Periodic lane restrictions are minimized on weekends and daytime hours.
- Two small detours will occur around the area of the wildlife crossings.
- Night work will occur, from 9 PM to 6 AM, away from town around MP 58.
Off-Alignment Construction
- Drilling and blasting will occur with noise mitigation measures in place.
- Minor trail reroutes will be posted during bridge access work.
Pioneer Road Improvements
- All access routes through subdivisions will remain open.
- Watch for increased truck traffic.
Know Before You Go
DOT&PF will notify the public about upcoming construction.
Project and road condition information
- AlaskaNavigator.org – construction status. Search for the Sterling Highway MP 45-60 project.
- 511.Alaska.Gov – road conditions – select “My 511” to create an account and sign up for alerts to your phone or email
- Sterlinghighway.net – project updates
Sign up now to receive alerts about changes to traffic patterns so you can plan your travel.
Station 6 - Public Meeting Video
Station 7 - Contact Us & Mailing List Sign-up
Comment - We want to hear from you!
Complete the CAPTCHA math equation to submit your comment.
Join our Emailing List!
Email Us
Visit the Project Website
Give us a call
Construction questions?
Shaun Combs, DOT&PF
907-351-0501
Project questions?
Katherine Wood
907-644-2153
Supporting Documents
The documents below support the information displayed throughout this online public meeting. You will need a PDF reader to view these documents. Download a free version at Adobe’s website.